A client asks for another page after reviewing the first layout. Compare the request with the approved scope. If the agreement covers two pages and the requested page is a third, describe exactly what it adds. Show the existing scope next to the proposed work and its effect on dates and cost.

Start by asking what the new page needs to accomplish. It may be a shorter version of a page already planned, or the client may need a new standalone page. See whether the change can replace something currently in scope. Show both options if they are actually possible.

Write a small change record

Item Sample entry
Existing scope Two informational pages with one shared review
Requested change Add a separate FAQ page and its navigation link
Fee effect Quote the new page and required review as an added amount
Date effect Move the first review by one workday after receiving the approved FAQ text
Approval Write down the approver, decision date, and changed scope version

The UK Office of the Small Business Commissioner recommends setting down the exact work and conditions in a written agreement. NYC DCWP’s sample contract also illustrates documenting services and compensation. Check your contract for its change process and follow any applicable legal requirements. Use the small change record to explain what needs written approval. UK Office of the Small Business Commissioner New York City Department of Consumer and Worker Protection

Decide whether the request is a correction or added work

Read the version the client approved and the current request side by side. If the scope includes a contact link and you left it out, correcting it may be part of completing the original job. If the client asks you to create a new contact page with an additional form, that can change the work. Ask what they need and point to the section that governs the original result. A quick conversation can reveal a misunderstanding about an existing deliverable. Mark a request as pending while you find out whether both sides can agree on the meaning.

Imagine the agreed work covers two informational pages and one review. The client now wants a frequently asked questions page. Ask for the draft questions and whether the page can replace one of the two. If they want three pages, give them an updated scope and check which dependencies change. The extra work may include a navigation update and review in another place, so price the complete change rather than the new page alone. If you can keep the delivery date when the new page replaces a different one, show that option with the tasks and approval required.

The UK Office of the Small Business Commissioner describes specifying services and conditions in a written contract. NYC DCWP’s example freelance agreement provides a place to record the work and payment under its context. Use your own agreement to find how a change becomes authorized and who can make it. Deal with any local requirements or ambiguous terms through the appropriate route for that project. UK Office of the Small Business Commissioner New York City Department of Consumer and Worker Protection

Show the person approving the change what happens next

Keep a one-paragraph record of the before and after. Use the project name, accepted version, proposed deliverable, price change, and earliest date you can finish after receiving required inputs. If the change affects acceptance, say which check the additional work will need. A note such as “add the FAQ page using approved answers, test its navigation link, and get one review from the named contact” lets the buyer see which tasks the fee covers. Tell them which existing milestone moves and how you will record the updated approval.

Suppose someone asks for a change during an informal call and the requester cannot approve the budget. Send the updated estimate to the named approver through the known project channel. Let the requester know what you need before starting. The original work can remain in progress where the new request does not affect it. If both parts compete for the same time, state which one would pause and ask for a choice. Record which approved dates still apply while the change is pending.

Check the work list and invoice after the decision

Once approved, update the working scope, delivery list, and invoice description to reference the same revision. If the client declined the change, leave it as a separate note and mark any later question that could reopen it. That can avoid confusion if a new reviewer sees the original request and asks why the work is absent. If the client moved a page from one milestone to another, check the agreed acceptance and payment events before issuing a bill. Send the right version to the people who need to know, including whoever collects the final feedback.

At the next checkpoint, ask whether everyone can identify the approved work. Look for gaps between what the client expects and what the team scheduled. If an unclear term caused the request, refine its example in a future agreement. If the client genuinely needed new work, save the estimate and the time it took so another similar change can be priced more reliably. The next action should follow the version both sides actually approved.

Give the client a choice they can use

A response might read “We can add the FAQ page after you supply the approved text. That adds $240 to the current scope and moves the first review to Tuesday. If the priority is keeping Monday, we can replace the overview page with the FAQ rather than adding a third page.” Use actual prices and dates you have checked.

If the client needs an immediate answer, tell them which effect you can confirm and which you need to recalculate. Keep the agreed work moving if the outstanding change does not affect it. Once the client approves, update the scope, schedule, and future invoice description to reflect the same version.

Check the work list after closing the change. Reassign tasks that moved and remove tasks the client replaced. If the request was declined or deferred, keep it in a separate list so it doesn’t reappear as a missed obligation.

When the change delays another task, send a revised timeline that shows the new approval dates.